Construction Update - August 2020
Stage 4 & 5 Kerb and Channel are underway, with electrical trenching starting this week. These stages are progressing well, and remain on track for anticipated settlement in October 2020.
Stage 6 Road Boxing is in progress. We have finished prepping the ground and will start to construct the lower layers of the road pavement. Installation of the water and gas mains and construction of kerb and channel will follow.
Stage 7 has had a busy month with trenching beginning for the sewer and drainage works.
The Anchoridge team are working hard behind the scenes to deliver on all requirements for the coming year, and we look forward to building your safehaven.